Former Laredo Air Force Base

Project Schedule

Return to History page

Project Schedule
as of June 2003
Duration
Item Activity 3/24 3/31 4/07 4/14 4/21 4/28 5/05 5/12 5/19 5/26 6/02 6/09 6/16 6/23 6/30 7/07 7/14 7/21 7/28 8/04 8/11 8/18 8/25 9/01 9/08 9/15 9/22 9/29
1 Background
Investigation
                                                       
2 Background Well
Sampling
                                                       
3 SCAPS in
Sanitary Landfill
                                                       
4 Sediment
Sampling
                                                       
5 Press Conference
(April 25th)
                                                       
6 Public Meeting
(May 1st)
                                                       
7 Public Meeting
(September 2003)
                                                       
8 Jet Engine Test Area and Paint
Shop Preliminary Investigation
                                                       
9 IWTP Environmental
Investigation
                                                       
10 Sanitary Landfill Environmental
Investigation
                                                       
11 Shot Gun Range Environmental
Investigation
                                                       
12 Reporting