Project Schedule
as of June 2003 |
Duration |
| Item |
Activity |
3/24 |
3/31 |
4/07 |
4/14 |
4/21 |
4/28 |
5/05 |
5/12 |
5/19 |
5/26 |
6/02 |
6/09 |
6/16 |
6/23 |
6/30 |
7/07 |
7/14 |
7/21 |
7/28 |
8/04 |
8/11 |
8/18 |
8/25 |
9/01 |
9/08 |
9/15 |
9/22 |
9/29 |
| 1 |
Background
Investigation |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 2 |
Background Well
Sampling |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 3 |
SCAPS in
Sanitary Landfill |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 4 |
Sediment
Sampling |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 5 |
Press Conference
(April 25th) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 6 |
Public Meeting
(May 1st) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 7 |
Public Meeting
(September 2003) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 8 |
Jet Engine Test Area and Paint
Shop Preliminary Investigation |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 9 |
IWTP Environmental
Investigation |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 10 |
Sanitary Landfill Environmental
Investigation |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 11 |
Shot Gun Range Environmental
Investigation |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 12 |
Reporting |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|